Partner Visa Appeal is a national Australian law firm that handles only Administrative Review Tribunal (ART) appeals for refused and cancelled partner visas. If your partner visa, subclass 820, 801, 309 or 100, has been refused or cancelled, you have 28 days to lodge an ART review application, or 14 days if you are in immigration detention. This deadline cannot be extended under any circumstances.

The deadline at a glance
| Your circumstance | Time to lodge an ART review application | Legal basis |
|---|---|---|
| Not in immigration detention | 28 days from deemed notification | Migration Act 1958, s347(3) |
| In immigration detention | 14 days from deemed notification | Migration Act 1958, s347(3) |
The clock runs from your deemed notification date under the Migration Act, not necessarily the date printed on the letter. The next section explains how that date is worked out.
This deadline cannot be extended
Section 347(3) of the Migration Act 1958 sets the 28-day and 14-day limits above. Section 347(5) then switches off the Tribunal's own general power to extend time, a power the Administrative Review Tribunal Act 2024 grants under section 19 for other matters, specifically for these applications. In practical terms, the ART has no discretion to accept a late partner visa review application, regardless of the reason for the delay. This is one of the few genuinely absolute rules in migration review, and it stands in contrast to the judicial review time limit described later on this page, which can be extended.

When does the clock actually start?
The 28-day or 14-day period runs from your deemed notification date, set by sections 494B and 494C of the Migration Act, which is frequently not the date printed on the decision letter.
| Method of notification | When the clock starts running |
|---|---|
| Handed to you in person | The date the document is actually received |
| Posted within Australia | 7 working days after the date on the document |
| Posted to an address outside Australia | 21 days after the date on the document |
| Sent by fax, email or other electronic means | The end of the day it was sent |
| Made available through ImmiAccount | The end of the day it was made available |
Note that the 21-day figure above is the international-post notification rule, a separate concept from the 28-day or 14-day deadline itself. The notification rule tells you when your clock starts; the 28-day or 14-day rule tells you how long that clock then runs.
Working out your own deemed notification date, and therefore your own true deadline, is not always straightforward.
Who this deadline applies to

The 28-day and 14-day limits apply to the person entitled to seek review, which is not always the visa applicant. For an onshore refusal or cancellation of a subclass 820 or 801 visa, the applicant generally applies. For a subclass 309 offshore refusal, only the sponsor may apply, not the visa applicant. For some subclass 100/801 permanent-stage offshore refusals, the applicant may apply only if physically in Australia both when refused and when lodging. These standing rules, from sections 338 and 347A of the Migration Act, sit alongside the time limit, not instead of it.
What happens if you miss the deadline
If a partner visa review application is not lodged within the applicable 28 or 14 days, the ART has no jurisdiction to accept it. There is no late-lodgement process and no case-by-case leniency. The original refusal or cancellation decision stands.
At that point, two avenues generally remain. The first is judicial review, confined to jurisdictional error, with no re-examination of the merits and no fresh evidence. It sits with the Federal Circuit and Family Court of Australia and carries its own 35-day time limit which, unlike the ART deadline, can be extended where necessary in the interests of justice. The second is a fresh visa application, which may be affected by a Section 48 Bar depending on the visa history involved.

What happens next if you act now
Acting inside the deadline keeps your options open. In general terms, the sequence looks like this:
1. Complete the Free Case Assessment
A short written screening tool covering your deadline and the basic shape of your case. This is not a consultation and not legal advice.
2. Paid consultation, if viable
If a review appears viable, a paid consultation is arranged, with a fixed-fee engagement set out in writing before any work begins.
3. Lodgement and fee payment
The ART review application is lodged and the Tribunal's fee is paid before the deadline, not merely lodged by then.
4. The review proceeds
The matter proceeds through the ART review process described in detail on our ART Appeal Process page.
Frequently asked questions
Disclaimer
This page provides general information about the ART review process. It is not legal advice. Every case turns on its own facts. Book a case assessment to discuss your circumstances.